17th Avenue Stormline
  • Install new dedicated stormwater pipe and inlet collection system
  • City Ditch pipe to remain

Schedule

Overall schedule:
  • July 2006 - January 2007
Specific milestones:
  • North side of street by August 2006
  • Center of street by October 2006
  • South side of street by early 2007

Photos

Click to enlarge


Construction Impacts in next 10 days

  • Project Complete
  • City to perform top coat paving in Summer 2007